Interagency AD Pay Plan Task Group
|
Charter, as amended
|
|
February 10, 2004
PURPOSE
To have the task group conduct an analysis of the pay plan to classify/level
positions to assure that they are in the appropriate category. Task
group is not to conduct review of rate settings, that task will be accomplished
by another assigned group.
SCOPE
The analysis should include all positions in the AD-1 through AD-5 classifications.
Findings will be used for future rate setting.
OBJECTIVES
The task group is to develop leveling tables that accurately reflect
the duties and responsibilities of all AD positions.
DELIVERABLES
The task group will review and finalize leveling process on all positions
in a final report to the IBPWT by August 15, 2004.
BUDGET
Funds are available to cover travel, per diem, and meeting room rental.
Cost tracking is required and performed by Group Leader. The tracking
should include salaries and agency-approved funding form task group
members.
Contact for budget is Hallie Locklear, 208-387-5166.
Task Group Leader, Judy Carvelho, USDA-FS
Carol Salo, USDI-BLM
Rosie Morin, USDI-BIA
Dana Stone, WYOMING STATE
Terri Knauth, USDA-FS
Loren Walker, USDA-FS
Jason Throngard, Classification Specialist
Sandra Tripp, Classification Specialist
Tony Recker, IBPWT Liaison
Ending August 15, 2004
ROLES AND RESPONSIBILITIES
Task Group
-
Perform evaluation from an interagency (versus agency-specific)
viewpoint.
-
Work as a team
-
Keep IBPWT Chair apprised of issues, concerns, and
progress
-
Request additional time or funds if needed
-
Utilize technical specialists identified
-
Identify and utilize other sources of information
as necessary
-
Complete task
-
Communicate with other working teams for advice and
guidelines
IBPWT
-
Ensure that the interagency community’s needs
are represented
-
Provide documentation gathered to date
-
Provide funding, oversight, and support
-
Keep agencies apprised of issues, concerns, and progress
-
Request additional time or funds if needed, from NWCG
-
Identify technical specialists for task group’s
use
-
Submit recommendations to agency representatives by
September 1, 2004
-
Work as a team
APPROVALS
Prepared & Submitted By:
| /s/ Judy Carvelho |
|
February 10, 2004 |
Judy Carvelho, Task Group Leader |
|
Date |
Approved By:
| /s/ Hallie Locklear |
|
February 10, 2004 |
Hallie Locklear, Chair
Incident Business Practices Working Team |
|
Date |
|
|
|