Skip to main content

Nozzle – Plastic, 35 GPM, 1” NPSH-F

NFES #
000138
Category
Water Handling
Updated
Storage and Shelf Life Checks
None

Initial Inspection/Disposal Criteria

  1. Inspect for burrs and cracks, broken plastic, or fire damage. Inspect gasket and replace if missing, cracked, or stiff.  Inspect for screw and nylon washer.  Inspect hose coupling threads for damage.
  2. Barrel must turn freely.
  3. Return to stock if nozzle functions properly, is free of damage and clean.
  4. Refurbish if nozzle is repairable.
  5. Dispose of any nozzle that is damaged beyond repair, has burn damage, or fails Testing for Performance and deficiencies cannot be corrected. Old style KK: Inspect threads inside of barrel; if they are damaged, dispose of nozzle.

Refurbishing Procedures

A. Testing for Performance

  1. Replace gasket if necessary.
  2. Connect nozzles to pump or manifold. Confirm connection ends are not out of round and there is no damage to threads.
    1. Pressure Test:
      1. Start pump.
      2. Make sure nozzles are open. Let all air escape. Shut nozzles.
      3. Pressurize to 300 PSI and hold for 3 minutes
  3. Inspect for leak:
    • Around the gasket
    • Behind the barrel
    • The tip of the barrel
      ​Note: Due to manufacturing processes a water tight shut-off seal on NFES #000137 and #000138 is very difficult to attain. Minimal drips or slight mist spray from the tip are acceptable for RFI condition.

B. Cleaning

  1. All items will be washed and cleaned of foreign matter, such as mud, dirt, and grease. Clean in a mild detergent with brush and scouring pad, or high pressure wash as needed. Do not soak for extended periods of time as the detergent will corrode the metal.
  2. Rinse thoroughly.
  3. Stand upright with barrel in open position to drain water and dry.
  4. Lubricate threads on back of the barrel with appropriate dry lubricant (graphite).

C. Repair

  1. Replace gaskets, washers or screws as needed.
  2. If plastic nozzle is found defective, dispose (NFES #000137, #000138).

D. Retesting

  • Following completion of any repairs, retesting of nozzles must be completed following Testing for Performance, above.

E. Repackaging

  • Stand upright and dry completely prior to repackaging.
    • Use NFES #008064 carton (10” x 8” x 6”)
    • Use NFES #008018 carton (12” x 12” x 6”) 10 PER CARTON 
    • Use NFES #008017 carton (18” x 12” x 10”) 60 PER CARTON

 

NWCG Latest Announcements

NWCG Welcomes the Incident Management Team Association as an Associate Member

Date: May 21, 2025
Questions?  Please contact:
https://www.nwcg.gov/contact-us

The NWCG Executive Board is honored to announce that the Incident Management Teams Association (IMTA) has joined the National Wildfire Coordinating Group as an associate member.

IMTA is a dedicated group of incident management professionals committed to enhancing the profession by promoting standards and fostering collaboration across federal, state, local, Tribal, and private sector partners throughout all phases of incident management.

“Joining NWCG aligns with our mission to elevate incident management professionals nationwide,” said Dr. Randal Collins, President of IMTA. “This is a proud moment for all of us committed to advancing public safety.”

References:

Incident Management Teams Association

National Wildfire Coordinating Group

Updated NWCG Guide for Wildland Fire Modules, PMS 431

Date: May 14, 2025
Questions?  Please contact:
Fire Use Subcommittee

The updated NWCG Guide for Wildland Fire Modules, PMS 431 serves as a supplemental resource for wildland fire module operations, providing information frequently used in the field.

PMS 431 defines the organizational structure, staffing, and qualifications for Type 1 and Type 2 Wildland Fire Modules, outlining their roles in wildland fire suppression, prescribed fire, and resource management. The NWCG Guide for Wildland Fire Modules, PMS 431, should be used in conjunction with the NWCG Standards for Wildland Fire Module Operations, PMS 430.

References:

NWCG Guide for Wildland Fire Modules, PMS 431

NWCG Standards for Wildland Fire Module Operations, PMS 430

Updated NWCG Standards for Wildland Fire Resource Typing, PMS 200 Now Includes Off-Highway Vehicle Typing Standards

Date: May 13, 2025
Questions?  Please contact:
Mobile Fire Equipment Subcommittee 

The NWCG Standards for Wildland Fire Resource Typing, PMS 200 has been updated to include newly developed Off-Highway Vehicle (OHV) typing standards. These standards organize OHV information into logical categories and outline key safety requirements for occupants.

NWCG Standards for Wildland Fire Resource Typing, PMS 200 establishes minimum typing standards for aircraft, crews, and equipment used in national mobilization to wildland fire incidents. Typing designations are assigned based on measurable capability and performance criteria.

References:

NWCG Standards for Wildland Fire Resource Typing, PMS 200

NEW! S-204, Interpersonal and Critical Thinking Skills for Safety Officers Now Available

Date: May 12, 2025
Questions?  Please contact:
Risk Management Committee

The S-204, Interpersonal and Critical Thinking Skills for Safety Officers self-directed online course is now available! Developed through the Incident Performance and Training Modernization (IPTM) effort, this training supports individuals working towards Safety Officer, Field (SOFF) incident qualifications.

S-204, Interpersonal and Critical Thinking Skills for Safety Officers focuses on facilitating hazard mitigation conversations and building trust to influence safety-related decisions. Individuals can self-enroll through the Wildland Fire Learning Portal (WFLP).

Any changes to qualification pathways will take effect with the next update of the NWCG Standards for Wildland Fire Position Qualifications, PMS 310-1.

References:

S-204, Interpersonal and Critical Thinking Skills for Safety Officers 

NWCG Safety Officer, Field (SOFF) Position Page

Wildland Fire Learning Portal