Aircraft

Helicopter Operations Risk Assessments

Aircraft | Facilities | Operations | Personnel Contractors | Personnel Government | Technology


SYSTEM:  Helicopter Operations, Aircraft

Sub-System Hazards Pre-Mitigation Mitigation Post-Mitigation

Probability

Severity

Risk Level

Probability

Severity

Risk Level

Capabilities High DA will over gross the aircraft

Possible

Catastrophic

Extremely High

Use appropriate aircraft for mission.  Conduct thorough pre-mission planning, load calculations, etc.  Reinforce HHH Training.

Unlikely

Catastrophic

High

Aircraft not appropriate for mission.  ICS Typing

Possible

Critical

High

Ensure appropriate aircraft is ordered and utilized.  Conduct thorough pre-mission planning, load calculations, etc.

Unlikely

Critical

Medium

Mechanical failure - flight component

Unlikely

Catastrophic

High

Follow NSHO, Ch 14, Scheduled Maintenance, Pre and Post Flight, etc.

Unlikely

Catastrophic

High

Equipment not well maintained and operational

Possible

Critical

High

Follow NSHO, Ch 9.  Ensure personnel receive adequate basic training.

Possible

Moderate

Medium

Visibility Lack of Hi Vis Aircraft Markings

Possible

Catastrophic

Extremely High

Identify paint schemes that are NOT highly visible and add that to the contract as NOT approved.

Rare

Catastrophic

Medium

Inspection Lack of standardization of government inspectors

Almost Certain

Critical

Extremely High

Recommend development and implement of interagency standardized inspection process. If one agency does not approve an aircraft or contractor for operation other agencies should follow and accept that decision.

Unlikely

Critical

Medium

Level of Training for HMGBs on inspection process is inadequate

Almost Certain

Moderate

High

Develop training for HMGB on MEL, maintenance buzz words (Watch Outs). Act on opportunity for HMGB to attend inspections.

Possible

Moderate

Medium

Equipment Personnel not proficient with equipment

Almost Certain

Moderate

High

Inspectors ensure Contractors (Pilots) are adequately trained and skilled with equipment provided. Ensure contract language requires equipment to be commensurate with current technology.

Possible

Moderate

Medium

Maintenance Maintenance in the field

Almost Certain

Critical

Extremely High

Fly aircraft to shop/hanger for maintenance whenever possible. Allow adequate time for mechanics to work in field.  Provide light/power/water if possible.

Unlikely

Critical

Medium

Lack of thorough documentation

Possible

Critical

High

Develop training for HMGB on MEL, Maintenance buzz words (Watch Outs). Enhance awareness through training for HMGB on when to call MI for assistance with Contractor and maintaining equipment.

Unlikely

Critical

Medium

Poor Communications between all parties (Contractor, GACC, CO, ACO, COR, PI, MI, HMGB)

Almost Certain

Critical

Extremely High

Enhance and integrate tracking of maintenance records AND Contract Evaluations of the aircraft over the duration of the contract period in order to recognize issues-CWN and Ex Use. Hire additional Maintenance Inspectors to keep up with this increased workload.

Possible

Critical

High

 

Download the Word version (docx) of this information and the Risk Assessment Matrix (pdf) to use with the Risk Assessment Worksheet (docx).

 

 

Last Modified / Reviewed:

NWCG Latest Announcements

New Aircraft Flight Schedule Form, PMS 249

Date:  April 17, 2026
Questions? 
Please contact: National Coordination System Committee

A new publication from the National Coordination System Committee (NCSC) is now available. The NWCG Aircraft Flight Schedule Form, PMS 249, will be used for aviation crews and dispatch to share flight information that is needed for resource tracking, and if needed, for emergency procedures.

For further details, please contact your NCSC representative. 

References:

NCSC Memo 26-01: Implementation of NWCG Aircraft Flight Schedule Form, PMS 249

NWCG Aircraft Flight Schedule Form, PMS 249

New Glossary Term for Review

Date:  April 15, 2026
Questions? 
Please contact: Data Standards and Terminology Board (DSTB)

The Data Standards and Terminology Board is requesting feedback on a new glossary term: Resource Protection Measure (RPM).

The proposed definition is: Practical guidance provided for incident personnel in a manner in which incident objectives can be achieved while reducing impacts to identified resources across the landscape. RPMs are informed by, but not restricted to, Minimum Impact Strategies and Tactics (MIST).

Please review, share with your subgroups, and provide feedback as appropriate through the following form: Request Feedback The comment period will close May 10, 2026.

Thank you for your engagement in the NWCG glossary process – your participation is key to our success.

References:

Glossary Request Feedback

Quarter Three Materials for the 2025-2026 Wildland Fire Leadership Campaign Now Available

Date:  April 1, 2026
Questions? 
Please contact: Leadership Committee

NWCG is excited to announce that Quarter Three materials for the 2025/2026 Wildland Fire Leadership Campaign are now available. This annual initiative offers all students of leadership and wildland fire management an opportunity to engage with essential leadership skills and knowledge needed to lead effectively in dynamic environments.

Quarter Three materials focus on Leadership Level 3: Leader of People (Develop Intent). Leadership Level 3 is where your values, your team, and your influence come together. Leaders of People put their teams first, build trust, and lead with authenticity. They mentor future leaders and shape decisions up and down the chain.

References:

2025/2026 NWCG Leadership Campaign - Leadership Levels

Wildland Fire Leadership Development Program

Leadership Committee

WFSTAR 2026 Core Components Module Package and 2025 Fire Year in Review Now Available

Date:  March 23, 2026
Questions? 
Please contact: Joe Schindel

The 2026 Core Components Module Package for RT-130, Wildland Fire Safety Training Annual Refresher (WFSTAR) and the 2025 Fire Year in Review are now available on the NWCG website. The 2026 Core Components Module Package provides all content needed to deliver RT-130.

References:

2026 Core Components Module Package

2025 Fire Year in Review Module